In Fill Projects – PROJECT TIMINGS

  • In fill measures must be completed within the 3 month time limit from the date of completed installation given on the associated qualifying measure​

  • For flats this is from the date of completed installation given and for houses from the date of completed installation of the third installed measure​

  • If in fill measures are not completed within this time the in fill measure will be rejected

  • A three month extension will be permitted for reasons that could not have been reasonably foreseen​

  • These include building fabric repairs found during the project or prolonged extreme weather​

  • Extensions will be awarded on a per-measure basis, not for the whole project​

  • Extensions will not be granted for in-fill measures​

  • Extensions will allow a total of six months from the date of completion of the first measure​

  • District heating connections are also eligible and will therefore receive a total of 9 months​

APPLY TODAY - It's FREE !

Let Us Check If You Are Eligible - For FREE!

If you are a landlord, homeowner or tenant, contact us today to see if you are eligible for FREE home upgrades!

Please ensure to include your house number and post code. Thank you

Give us a ring
Send us an email